1, regardless of the installation method of the base, it must be guaranteed to do the following.
(1) The upper working surface of the chassis should be located on the same horizontal surface, and its level is applied to the level or a level.
(2) The mounting line A-A placed on the longitudinal center of the two chassis should be parallel and must be perpendicular to the cylindrical axis K-K.
(3) The mounting line B-B drawn by the two chassis horizontal line should be coincident with K-K.
2, the spindle size of the feed end cover must be slightly moved outward by the nominal size of the installation to meet the needle (finger-drying) of the cylinder due to heat.
1) , the ground bolt hole should not be filled with cement in the whole length, but should be over the upper end of the bolt.
2) , the base should be poured twice after all the ball mills are finished.
3) , clean dust and carefully cleans the bearings and reservoirs with kerosene.
4) , bearing liners should be gently placed on the bearing base to avoid damaging due to impact.
5) , the given cooling water pipe joint is assembled.
6) , the oil supply device and the main bearing cover should be in the rotating portion (cylinder and inward, discharge portion) of the ball mill, and then install it after being corrected.
7) . When installing the oil supply device, adjust the gap of the scraper and the oil circle, prohibit the anti-card death, so that the oil supply work is smooth.